1.30.1 CO01
ACTIVITY DESCRIPTION SHEET (ADS)
PROJECT:
GAS Plant FEED Design
REV.:
0
PROJECT AREA
Level 1
FEED - Front End Engineering Design
DISC: IT
SUB-AREA
Level 2
Overhead transmission Line (including substation upgrade)
 
 
ACTIVITY
Level 3
Constructabilty Report
CODE:CO01
ACTIVITY DESCRIPTION:
Development of the constructability report including at least the following topics:
  • contract strategy,
  • Project execution plan,
  • construction philosophy management plan,
  • provisional logistic philosophy & plan
  • provisional construction execution plan,
  • provisional temporary facilities plan
  • provisional soil management plan,
  • work packages plan (WBS),
  • local fabrication capacity assumption,
  • general indication of transportation system with preliminary oversize shipping shedule,
  • construction environmental management plan (HOLD).
INPUT DATA:
General lay out new and existing facilities location,
preliminary new plot plans,
Basic equipment list,
major equipment packages estimated data,
process flow diagram,
existing logistic survey,
existing local facilities survey,
soil and environmental data
 
DELIVERABLES:
  • Constructability report
 
NOTES:
Logistic and local facilities survey to be provided by Company
 