ACTIVITY
DESCRIPTION SHEET (ADS)
|
PROJECT:
|
GAS Plant FEED
Design
|
REV.:
|
0
|
PROJECT AREA
Level
1
|
FEED - Front End
Engineering Design
|
DISC: IT
|
SUB-AREA
Level
2
|
Gas Sweetening
Plant
|
|
ACTIVITY
Level
3
|
Construction Plan
|
CODE:CO02
|
ACTIVITY DESCRIPTION:
|
Development of the construction and installation plan package which
shall included the following: construction plans both site and
plant,
- temporary
site facilities both construction personnel living camp and site
work shop and storage area,
- summer
and winter work planning,
-
construction and installation man-hours schedule both direct and
indirect with field direct and indirect estimates,
-
construction and installation tentative schedule,
-
preparation and follow up for the installation/ construction
budgetary offers
-
Transportation review for major items
- Heavy
equipment lift study.
-
Warehousing philosophy
|
INPUT
DATA:
|
Location lay out including both new and existing plant,
plant plot plan,
equipment list,
major equipment/packages data,
P&ID.s,
preliminary piping and cables routing,
piping electrical/instr. bulk material
preliminary bill of quantities,
one line main structures drawings,
preliminary foundation and architectural plans
and estimated material quantities,
one line electrical diagrams,
PAU merging solution,
existing logistic survey,
existing local
facilities survey.
|
DELIVERABLES:
|
-
construction
Execution plan and strategy
-
Construction
Schedule
-
plan for
temporary facilities camp & work areas
|
NOTES:
|
Logistic and local
facilities survey to be provided by Company
|
|
|
|
|