ACTIVITY
DESCRIPTION SHEET (ADS)
|
PROJECT:
|
GAS Plant FEED
Design
|
REV.:
|
0
|
PROJECT AREA
Level
1
|
FEED - Front End
Engineering Design
|
DISC:
CIVIL
|
SUB-AREA
Level
2
|
Offsite Design Lagoon
– External Roads
|
|
ACTIVITY
Level
3
|
Civil Technical
Specification
|
CODE: CV20
|
ACTIVITY DESCRIPTION:
|
-
To review Client supplied
documentation, specification, design criteria, drawings and reports
;
-
To identify omissions to data
required (if any);
-
To prepare/update the design data
to be used for the FEED design of the structures, including List of
applicable Codes, Standards, Specifications and
Regulations;
-
List of environmental, geotechnical
and seismological data.
-
List of main data and materials
properties;
-
Accurate analysis of the geological
and geotechnical data, examination of all the geotechnical aspects
for a correct design;
-
To classify the soils typology
according to the geological and geotechnical report in order to the
proper technological choice;
-
Description of the design criteria
applicable to various aspects of the design, for the temporary and
the permanent condition;
-
To define all construction
requirements (proper material selection, definition material
package , etc..);
-
To define the typical roads section
according to the design premises, boundary conditions and
functional requirements;
-
To define Roads routing and
geometry (maximum longitudinal slope, transversal slope, width,
minimum inside radius);
The activity will
be developed in conjunctions, and supported by, the other
disciplines. The Activity will be carried out with a continuous
check and monitoring of the interfaces with other disciplines and
other Contractors, in order to ensure a the congruence of the
performed FEED design activities with the overall project design
process.
|
INPUT
DATA:
|
-
Contract Technical Documentation /
Feasibility Design.
-
Basis of Design
-
General Safety
Criteria
-
Environmental
Report
-
Geological/Geotechnical
Report
-
Seismological Report (if
any).
|
DELIVERABLES:
|
-
Specification for Site Preparation
and earthworks;
-
Specification for Lagoon Civil
Works;
-
Specification for Roads
Works;
-
Specification for Material
Selection;
|
NOTES:
|
|
|
|
|
|