PROJECT:
|
GAS Plant FEED
Design
|
REV.:
|
0
|
PROJECT AREA
Level
1
|
FEED - Front End
Engineering Design
|
DISC:
CIVIL
|
SUB-AREA
Level
2
|
Gas Sweetening
Plant
|
|
ACTIVITY
Level
3
|
Civil and Land Surveys (Topografical, Geological
,Geotechnical, Resistivity etc.) - Pipelines/Offsites
|
CODE: CV91
|
ACTIVITY DESCRIPTION:
|
-
Desk study of the existing Reports
and review of available hydrological / hydro-meteorological
data.
-
Review & Finalisation of
topographical survey requirement.
-
Follow-on about topographic survey
as per submitted specification;
-
General layout planning of schemes
on toposheets / survey sheets,
-
Reconnaissance visit to project
sites;
-
Technical advice in establishment
of hydro-metrological station, if needed.
-
Desk study for alternate
Layout.
-
Geological assessment (surface) of
the project area and Geological & Geotechnical
Investigation;
-
Flood studies GIS (Geographical
information system) studies for flood data.
-
Geological mapping of the project
area.
-
Follow-on about topographic survey
as per submitted specification;
-
Construction methodology and
equipment planning.
-
Preparation of Final Site Survey
Report incorporating observations, if any, of the
client.
|
INPUT
DATA:
|
-
Contract Technical Documentation /
Feasibility Design
-
Basis of Design
-
General Safety
Criteria
-
Pipeline Rout Layout ;
;
|
DELIVERABLES:
|
-
Site Survey
specification;
-
Site Survey
Report;
|
NOTES:
|
|
|
|
|
|