ACTIVITY
DESCRIPTION SHEET (ADS)
|
PROJECT:
|
GAS Plant FEED
Design
|
REV.:
|
0
|
PROJECT AREA
Level
1
|
FEED - Front End
Engineering Design
|
DISC: ELE
|
SUB-AREA
Level
2
|
Over Head Transmission
Line
|
|
ACTIVITY
Level
3
|
Substation
interlocking
|
CODE:OH11
|
ACTIVITY DESCRIPTION:
|
- Prepare
the electrical protection diagrams of the substation with the
interlocking and intertripping diagrams
- Prepare
the power distribution and control system equipments.
|
INPUT
DATA:
|
- Technical
Documentation / Feasibility Design
-
Electrical substation one line diagram.
|
DELIVERABLES:
|
-
Substation protection diagrams
-
Electrical substation interlocking and intertripping diagrams
- Automatic
transfer diagrams
-
Definition of power distribution control system equipments
(PDCS)
|
NOTES:
|
|
|
|
|
|