ACTIVITY
DESCRIPTION SHEET (ADS)
|
PROJECT:
|
Gas Plant FEED
Design
|
REV.:
|
0
|
PROJECT AREA
Level
1
|
Management and
Administration
|
DISC:
PROJ.MAN
|
SUB-AREA
Level
2
|
Project Management and
Administration
|
|
ACTIVITY
Level
3
|
Development of Risk
Management Plan
|
CODE: PM07
|
ACTIVITY DESCRIPTION:
|
Risk Management is an ongoing activity that ensures appropriate
activity on Risk Mitigation.
Two types of activity (1) Identification and (2)
Evaluation are conducted by the Value Risk function in a continuous
cycle that works towards achievement of clarity in the contents of
the Risk Register.
Establishment of the Risk Management Plan is
substantially completed before the FEED phase but further
development is necessary to integrate requirements that arise from
new discovery of project risks.
Project Team to provide assistance to the Value
Risk function in the gathering of Risk Data and participation in
workshops and interviews.
Project Team to take part in Risk Reviews,
including the results of incorporation of gathered data into the
Risk Register.
|
INPUT
DATA:
|
Data from Workshops and Interviews.
Risk Register
|
DELIVERABLES:
|
Risk Management Plan
Risk Register
|
NOTES:
|
SoW Ref: 7.2.2
|
|
|
|
|